Selected projects

Terminal expansion, Botlek

2025 — procurement and inspection of 42 valves and 6 pump units for a new jetty line. Delivered in four shipments, all documents in the commissioning file before start-up.

Shipyard re-equipment, Gdansk

2024 — replacement of plate handling equipment. Vendor search in three countries, witness tests at two works, delivery by project cargo in eleven weeks.

Spare parts baseline, Moerdijk

2024 — review of 1 800 stock positions, obsolete items flagged, recommended spare list per asset. Stock value reduced by 14% in the first year.

Emergency sourcing, Vlissingen

2023 — seal failure on a crude transfer pump. Replacement located and flown in within 36 hours; pump back in service the same weekend.